{"id":701,"date":"2017-10-03T13:23:56","date_gmt":"2017-10-03T11:23:56","guid":{"rendered":"http:\/\/www.primanedacademy.com\/demo\/?p=701"},"modified":"2017-12-20T14:27:33","modified_gmt":"2017-12-20T13:27:33","slug":"value-as-a-knowledge-area-project-controls","status":"publish","type":"post","link":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/","title":{"rendered":"Value as a knowledge area of Project Controls"},"content":{"rendered":"<p>Project management is defined by the PMBoK, as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d. But what are those requirements that need to be met?<\/p>\n<p><!--more--><\/p>\n<h4>The classical approach of project management<\/h4>\n<p>According to the traditional project management approach, a project is successful if the expected object is delivered in compliance with specifications, within schedule and within budget. In other words, fulfilling the so-called triple constraint of project management \u2013 Scope, Schedule and Cost. These three constraints are mutually dependent and equally important, justifying their graphical representation and the alternative naming given to the triple constraint: The iron triangle of Project Management.<\/p>\n<p>&nbsp;<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"size-full wp-image-707 aligncenter\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Fig_1_ValueofknowledgePC.png\" alt=\"\" width=\"159\" height=\"127\" \/>Most of the scholars\u2019 research and related bibliography in the project management field was focused on this approach, even in recent years. This is justifiable, regarding the public attention towards the project\u2019s time and cost overruns \u2013 figures with a very immediate and tangible nature.<\/p>\n<p>Over time, practitioners tried to refine this approach which naturally started to evolve. In the first model, quality was considered part of Scope. It was then isolated and regarded as a result of all three constraints. This triangle became a diamond, with Quality being the fourth corner. Finally, the 4<sup>th<\/sup> edition of the PMBoK developed a six-point star, which also includes Risk and Resources as constraints that need to be weighed.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"size-full wp-image-706 alignleft\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Fig_2_ValueofknowledgePC.png\" alt=\"\" width=\"159\" height=\"127\" \/><img loading=\"lazy\" decoding=\"async\" class=\"alignnone size-full wp-image-705\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Fig_3_ValueofknowledgePC.png\" alt=\"\" width=\"189\" height=\"157\" \/><img loading=\"lazy\" decoding=\"async\" class=\"alignnone size-full wp-image-704\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Fig_4_ValueofknowledgePC.png\" alt=\"\" width=\"168\" height=\"161\" \/><\/p>\n<p>Yet, a successful balance of those constraints was not enough to ensure project success. Practitioners realized that sometimes projects, after delivery, didn&#8217;t satisfy the clients or the users, even if they met all the requirements. The typical project management approach, even after all developments, was not weighing this crucial element, the end user satisfaction.<\/p>\n<p>Satisfying needs is a primary goal in any project. So, shouldn\u2019t this be a main constraint to be assessed?<\/p>\n<h4>The new trend of project management<\/h4>\n<p>Recently, a new trend within the project management field started to emerge.<\/p>\n<p>People implement projects because they want to improve their lives. Organizations implement projects because they want to increase their potential. Nations implement projects to grow and enhance social conditions. Whatever the project, whoever its owner or sponsor, projects are implemented with a goal, a goal to change and add value to people and \/ or organizations.<\/p>\n<p>Value is the core subject of this new trend. The value that a project adds will determine the satisfaction of the end users. For the project to be successful, it must be valuable for those who are impacted by it, especially the end users. This is perhaps even more important than meeting all six previously listed requirements.<\/p>\n<p>The word Value is a subjective concept, related to the different perception of every single person and the field where it is applied. In project terms, though, Value can be defined as the ability to satisfy needs of stakeholders, not only with the project implementation but also (long) after its completion.<\/p>\n<p>With this approach, project life-cycle doesn\u2019t end with its delivery. This is the main difference between Value and the other constraints that project managers urge to deal with. While all six traditional requirements focus on what the project produces, i.e. the outputs, Value refers to the difference these outputs will make to the stakeholders, i.e. the outcomes of a project. So, Value can be judged by the benefits (and \u201cdis-benefits\u201d) coming forth from the project.<\/p>\n<h4>Value controls of a project<\/h4>\n<p>The expected benefits of a project are listed and described in the business case. These benefits must be somehow measurable, as they will act as the indicators for\u00a0 the creation of value.<\/p>\n<p>However, benefit realization and, consequently, value creation were never seen before as a project management duty. In fact, many times it was no one\u2019s duty. With so many projects failing to add value, practitioners realized that a bridge between business and execution was missing. Therefore, they conclude \u201cthe application of knowledge, skills, tools, and techniques to project activities\u201d should also focus on the creation of value.<\/p>\n<p>Of course, the job of certifying that\u00a0 anticipated value is indeed added by the project is not an easy one. Simply assuring the anticipated benefits are going to be delivered might not be enough. The project must be constantly assessed against its business case, to ensure it\u2019s still valid: the stakeholders\u2019 needs might change, the environmental factors are mutable with time, etc.<\/p>\n<p>As you have just read, it is crucial to \u201ccapture, model, analyze, predict, measure, report and inform\u201d value-related data, at any given moment of the project life-cycle, so it is possible to \u201cdeliver insights of the project that will improve decision making, ensuring the projects will deliver maximal value to the stakeholders\u201d. This is why Primaned Belgium considers Value now as part of the knowledge areas of Project Controls, just like the ones previously listed and defined in one of our blog posts, <a href=\"https:\/\/primaned.be\/en\/2017\/04\/27\/project-controls-noodzakelijke-definitie\/\">\u201cProject Controls \u2013 A Definition\u201d<\/a>, which can be represented in the following figure.<\/p>\n<p>&nbsp;<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-711 size-large\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Areas-1-1024x126-1024x126.png\" alt=\"\" width=\"1024\" height=\"126\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Areas-1-1024x126.png 1024w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Areas-1-1024x126-300x37.png 300w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/Areas-1-1024x126-768x95.png 768w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/>Controlling value is not an easy task and few are the ones that already do it in their projects. Here in Primaned, we want to be the front runners in this field and thus we are investing in knowledge and expertise to develop a set of techniques, that we believe will enhance Value control and lift Project Controls to another level. The tools we proposed will be described in later blog posts.<\/p>\n<p><strong>This blog has been originally posted on\u00a0<a href=\"https:\/\/primaned.be\/en\/value_of_project_controls\/\">Primaned.be<\/a>\u00a0on 3 October 2017.<\/strong><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Project management is defined by the PMBoK, as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d. But what are those requirements that need to be met?<\/p>\n","protected":false},"author":8,"featured_media":703,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"footnotes":""},"categories":[87],"tags":[91,108],"class_list":["post-701","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog-en","tag-primaned-academy-en","tag-quality"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.4 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Value as a knowledge area of Project Controls - Primaned Academy<\/title>\n<meta name=\"description\" content=\"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/\" \/>\n<meta property=\"og:locale\" content=\"en_GB\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Value as a knowledge area of Project Controls - Primaned Academy\" \/>\n<meta property=\"og:description\" content=\"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/\" \/>\n<meta property=\"og:site_name\" content=\"Primaned Academy\" \/>\n<meta property=\"article:published_time\" content=\"2017-10-03T11:23:56+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2017-12-20T13:27:33+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"600\" \/>\n\t<meta property=\"og:image:height\" content=\"398\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Jo\u00e3o Miranda\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Jo\u00e3o Miranda\" \/>\n\t<meta name=\"twitter:label2\" content=\"Estimated reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"5 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/\"},\"author\":{\"name\":\"Jo\u00e3o Miranda\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/e2c2733efcba5ca94894c0f50c055260\"},\"headline\":\"Value as a knowledge area of Project Controls\",\"datePublished\":\"2017-10-03T11:23:56+00:00\",\"dateModified\":\"2017-12-20T13:27:33+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/\"},\"wordCount\":913,\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/ValueofknowledgePC.jpg\",\"keywords\":[\"Primaned Academy\",\"Quality\"],\"articleSection\":[\"Blog - EN\"],\"inLanguage\":\"en-GB\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/\",\"name\":\"Value as a knowledge area of Project Controls - Primaned Academy\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/ValueofknowledgePC.jpg\",\"datePublished\":\"2017-10-03T11:23:56+00:00\",\"dateModified\":\"2017-12-20T13:27:33+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/e2c2733efcba5ca94894c0f50c055260\"},\"description\":\"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#breadcrumb\"},\"inLanguage\":\"en-GB\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/ValueofknowledgePC.jpg\",\"contentUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/ValueofknowledgePC.jpg\",\"width\":600,\"height\":398},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/value-as-a-knowledge-area-project-controls\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Value as a knowledge area of Project Controls\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/\",\"name\":\"Primaned Academy\",\"description\":\"Opleidingen in Projectbeheersing \\\/ Project Controls\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.primanedacademy.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-GB\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/e2c2733efcba5ca94894c0f50c055260\",\"name\":\"Jo\u00e3o Miranda\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g\",\"caption\":\"Jo\u00e3o Miranda\"},\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/author\\\/joao\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Value as a knowledge area of Project Controls - Primaned Academy","description":"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/","og_locale":"en_GB","og_type":"article","og_title":"Value as a knowledge area of Project Controls - Primaned Academy","og_description":"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d","og_url":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/","og_site_name":"Primaned Academy","article_published_time":"2017-10-03T11:23:56+00:00","article_modified_time":"2017-12-20T13:27:33+00:00","og_image":[{"width":600,"height":398,"url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg","type":"image\/jpeg"}],"author":"Jo\u00e3o Miranda","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Jo\u00e3o Miranda","Estimated reading time":"5 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#article","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/"},"author":{"name":"Jo\u00e3o Miranda","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/e2c2733efcba5ca94894c0f50c055260"},"headline":"Value as a knowledge area of Project Controls","datePublished":"2017-10-03T11:23:56+00:00","dateModified":"2017-12-20T13:27:33+00:00","mainEntityOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/"},"wordCount":913,"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg","keywords":["Primaned Academy","Quality"],"articleSection":["Blog - EN"],"inLanguage":"en-GB"},{"@type":"WebPage","@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/","url":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/","name":"Value as a knowledge area of Project Controls - Primaned Academy","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#primaryimage"},"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg","datePublished":"2017-10-03T11:23:56+00:00","dateModified":"2017-12-20T13:27:33+00:00","author":{"@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/e2c2733efcba5ca94894c0f50c055260"},"description":"Project management is defined as \u201cthe application of knowledge, skills, tools and techniques to project activities to meet the project requirements\u201d","breadcrumb":{"@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#breadcrumb"},"inLanguage":"en-GB","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/"]}]},{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#primaryimage","url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg","contentUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/ValueofknowledgePC.jpg","width":600,"height":398},{"@type":"BreadcrumbList","@id":"https:\/\/www.primanedacademy.com\/en\/value-as-a-knowledge-area-project-controls\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.primanedacademy.com\/en\/"},{"@type":"ListItem","position":2,"name":"Value as a knowledge area of Project Controls"}]},{"@type":"WebSite","@id":"https:\/\/www.primanedacademy.com\/#website","url":"https:\/\/www.primanedacademy.com\/","name":"Primaned Academy","description":"Opleidingen in Projectbeheersing \/ Project Controls","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.primanedacademy.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-GB"},{"@type":"Person","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/e2c2733efcba5ca94894c0f50c055260","name":"Jo\u00e3o Miranda","image":{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/secure.gravatar.com\/avatar\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/ed5a4b6a615f675c05f77378d47776427185f2a443b955d4faeeb904c4f700ff?s=96&d=mm&r=g","caption":"Jo\u00e3o Miranda"},"url":"https:\/\/www.primanedacademy.com\/en\/author\/joao\/"}]}},"_links":{"self":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/701","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/comments?post=701"}],"version-history":[{"count":5,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/701\/revisions"}],"predecessor-version":[{"id":1852,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/701\/revisions\/1852"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/media\/703"}],"wp:attachment":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/media?parent=701"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/categories?post=701"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/tags?post=701"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}