{"id":3437,"date":"2019-06-13T11:11:03","date_gmt":"2019-06-13T09:11:03","guid":{"rendered":"https:\/\/www.primanedacademy.com\/?p=3437"},"modified":"2023-01-17T17:12:01","modified_gmt":"2023-01-17T16:12:01","slug":"change-control-4-levels-of-change","status":"publish","type":"post","link":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/","title":{"rendered":"Change Control: 4 Levels of Change"},"content":{"rendered":"<p>Gert Truyens explains what the different levels of change are, what they mean and how you can deal with them.<\/p>\n<p>Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.<!--more--><\/p>\n<p>A first step which proved to be of great help, is differentiating between several levels of change. To do this, we start by defining 5 levels on which projects are managed.<\/p>\n<h2>5 Levels of managing projects<\/h2>\n<p>Project team members and corporate management deal with different levels of management.<\/p>\n<ol>\n<li>A project is stemmed by a\u00a0<strong>business need<\/strong>\u00a0from the parental organization, i.e. the why of the project. Corporate management must guard the alignment of the project with the company, or in other words: the existing organization\u2019s governance should be supported by the project governance.<\/li>\n<li>The\u00a0<strong>project charter<\/strong>\u00a0is on the second level: it delimits the scope, objectives and responsibilities of the project mandate. These are translated into the boundaries of the project contract: contractual scope, milestones and price. The Contractor must execute the project within these boundaries. At this level a\u00a0<u>funding reserve<\/u>\u00a0(both time and budget) may be available to cover the project owner risks. Exceeding the boundaries may lead to\u00a0<em>variation orders<\/em>.<\/li>\n<li>Within those contractual boundaries, a project\u00a0<strong>baseline<\/strong>\u00a0is set. This is the agreed plan to execute the project and monitor progress against a set baseline scope, schedule and cost. It is the responsibility of the PM to deliver the project within the boundaries of this baseline. Where at level 2 it is the project owner that owns the funding reserve, similarly at level 3 e.g. the project board owns the\u00a0<u>management reserve<\/u>\u00a0which covers unknown unknowns. Eventual exceedances of the baseline can lead to\u00a0<em>baseline updates<\/em>.<\/li>\n<li>Based on monitored progress, the project should have at any time a\u00a0<strong>current plan<\/strong>\u00a0including a new forecast of the remaining activities, i.e. the estimate at completion. At this level, the PM has the\u00a0<u>contingency reserve<\/u>\u00a0at his disposal to cover project risks. Deviations from the current plan are\u00a0<em>variances\u00a0<\/em>and might require preventive and corrective actions.<\/li>\n<li>At the lowest level, smaller activity level deviations are monitored. I like to call this the\u00a0<strong>executional<\/strong>\u00a0or operational level where deviations don\u2019t require replanning. At this level, you accept that the work cannot be executed exactly according to plan, minute by minute. You measure, monitor and report progress resulting in the actual schedule and actual costs.<\/li>\n<\/ol>\n<h2>4 Levels of change<\/h2>\n<p>When a change is identified, understanding the type or level of change you are dealing with is a first step that will greatly help you structuring the change management process. It is the association with one of the levels of project management that will help you categorizing changes. This in its turn will than guide the team in dealing with the change. In the model below (Figure 1: 4 levels of change), you can see that levels 1 to 4 are subject to change.<\/p>\n<p>At the 5th level, we only talk about \u2018events\u2019 and not change: it\u2019s merely the daily progress monitoring and control process. However, those events can lead to change on a higher level. In general, higher level changes will impact all lower levels, and lower level changes might or might not lead to changes at higher levels.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"wp-image-3440 aligncenter\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg\" alt=\"\" width=\"902\" height=\"421\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg 300w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-768x358.jpg 768w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-1024x478.jpg 1024w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6.jpg 1140w\" sizes=\"auto, (max-width: 902px) 100vw, 902px\" \/><\/p>\n<p>Fig.1 \u2013 4 levels of change<\/p>\n<ol>\n<li>Change at\u00a0<u>level one<\/u>\u00a0is related to an update of the\u00a0<strong>business case<\/strong>. For example, changing the type of contract or the subject of the contract (a bridge is changed to a tunnel to state an extreme example). This type of change will impact all other levels as well.<\/li>\n<li>A\u00a0<u>level two<\/u>\u00a0change would require changes to the\u00a0<strong>project boundaries<\/strong>, which are often amendments to the contract. Variation orders would resort under this category (for example scope changes), but also a change of a contractual milestone is a typical level two change.<\/li>\n<li>Changes at\u00a0<u>level three<\/u>\u00a0would entail\u00a0<strong>baseline<\/strong>\u00a0updates of the\u00a0<em>current<\/em>\u00a0project scope, meaning that here you stay within the project boundaries (hence the difference between level two and three). A typical example here is a variation order at level 2 that leads to a baseline update at level 3. Also in an Earned Value Management context, a management reserve transaction would typically update the baseline, without affecting the boundaries and is thus a level three change.<\/li>\n<li>Deviating from the plan usually doesn\u2019t initiate a baseline change. At\u00a0<u>level four<\/u>, a change can lead to replanning of the remaining work by taking mitigation measures. For example, resequencing some activities to accelerate completion would occur at this level.<\/li>\n<\/ol>\n<h2>Conclusion<\/h2>\n<p>Being aware of the level at which a change occurs is a crucial step to start the change control process with. How you deal with changes is highly dependent on the level. If you want to become the expert in this field or you can use some guidance at your current project, Primaned\u2019s \u201cChange Control and Claim Analysis\u201d training might be just what you need.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Gert Truyens explains what the different levels of change are, what they mean and how you can deal with them. Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project [&hellip;]<\/p>\n","protected":false},"author":7,"featured_media":0,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"footnotes":""},"categories":[87],"tags":[],"class_list":["post-3437","post","type-post","status-publish","format-standard","hentry","category-blog-en"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.4 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Change Control: 4 Levels of Change - Primaned Academy<\/title>\n<meta name=\"description\" content=\"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/\" \/>\n<meta property=\"og:locale\" content=\"en_GB\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Change Control: 4 Levels of Change - Primaned Academy\" \/>\n<meta property=\"og:description\" content=\"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/\" \/>\n<meta property=\"og:site_name\" content=\"Primaned Academy\" \/>\n<meta property=\"article:published_time\" content=\"2019-06-13T09:11:03+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2023-01-17T16:12:01+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg\" \/>\n<meta name=\"author\" content=\"Gert Truyens\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Gert Truyens\" \/>\n\t<meta name=\"twitter:label2\" content=\"Estimated reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/\"},\"author\":{\"name\":\"Gert Truyens\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/1b344aab52f77aa5da3475faf03263cd\"},\"headline\":\"Change Control: 4 Levels of Change\",\"datePublished\":\"2019-06-13T09:11:03+00:00\",\"dateModified\":\"2023-01-17T16:12:01+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/\"},\"wordCount\":854,\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/foto-change-control-13-6-300x140.jpg\",\"articleSection\":[\"Blog - EN\"],\"inLanguage\":\"en-GB\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/\",\"name\":\"Change Control: 4 Levels of Change - Primaned Academy\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/foto-change-control-13-6-300x140.jpg\",\"datePublished\":\"2019-06-13T09:11:03+00:00\",\"dateModified\":\"2023-01-17T16:12:01+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/1b344aab52f77aa5da3475faf03263cd\"},\"description\":\"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#breadcrumb\"},\"inLanguage\":\"en-GB\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/foto-change-control-13-6-300x140.jpg\",\"contentUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/foto-change-control-13-6-300x140.jpg\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/change-control-4-levels-of-change\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Change Control: 4 Levels of Change\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/\",\"name\":\"Primaned Academy\",\"description\":\"Opleidingen in Projectbeheersing \\\/ Project Controls\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.primanedacademy.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-GB\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/1b344aab52f77aa5da3475faf03263cd\",\"name\":\"Gert Truyens\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g\",\"caption\":\"Gert Truyens\"},\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/author\\\/gert\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Change Control: 4 Levels of Change - Primaned Academy","description":"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/","og_locale":"en_GB","og_type":"article","og_title":"Change Control: 4 Levels of Change - Primaned Academy","og_description":"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.","og_url":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/","og_site_name":"Primaned Academy","article_published_time":"2019-06-13T09:11:03+00:00","article_modified_time":"2023-01-17T16:12:01+00:00","og_image":[{"url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg","type":"","width":"","height":""}],"author":"Gert Truyens","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Gert Truyens","Estimated reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#article","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/"},"author":{"name":"Gert Truyens","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/1b344aab52f77aa5da3475faf03263cd"},"headline":"Change Control: 4 Levels of Change","datePublished":"2019-06-13T09:11:03+00:00","dateModified":"2023-01-17T16:12:01+00:00","mainEntityOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/"},"wordCount":854,"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg","articleSection":["Blog - EN"],"inLanguage":"en-GB"},{"@type":"WebPage","@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/","url":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/","name":"Change Control: 4 Levels of Change - Primaned Academy","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#primaryimage"},"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg","datePublished":"2019-06-13T09:11:03+00:00","dateModified":"2023-01-17T16:12:01+00:00","author":{"@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/1b344aab52f77aa5da3475faf03263cd"},"description":"Managing change will always be a challenge in projects. Its importance cannot be overestimated in order to successfully deliver projects. Messing up will have huge implications in a claim-oriented environment. Still we see many project teams struggling with organizing and following a proper change management process.","breadcrumb":{"@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#breadcrumb"},"inLanguage":"en-GB","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/"]}]},{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#primaryimage","url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg","contentUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/foto-change-control-13-6-300x140.jpg"},{"@type":"BreadcrumbList","@id":"https:\/\/www.primanedacademy.com\/en\/change-control-4-levels-of-change\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.primanedacademy.com\/en\/"},{"@type":"ListItem","position":2,"name":"Change Control: 4 Levels of Change"}]},{"@type":"WebSite","@id":"https:\/\/www.primanedacademy.com\/#website","url":"https:\/\/www.primanedacademy.com\/","name":"Primaned Academy","description":"Opleidingen in Projectbeheersing \/ Project Controls","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.primanedacademy.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-GB"},{"@type":"Person","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/1b344aab52f77aa5da3475faf03263cd","name":"Gert Truyens","image":{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/secure.gravatar.com\/avatar\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/df84016ac04f112908e04acad80a43f194ee96dc84eef6185e931b78689bc6ff?s=96&d=mm&r=g","caption":"Gert Truyens"},"url":"https:\/\/www.primanedacademy.com\/en\/author\/gert\/"}]}},"_links":{"self":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/3437","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/users\/7"}],"replies":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/comments?post=3437"}],"version-history":[{"count":6,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/3437\/revisions"}],"predecessor-version":[{"id":5152,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/3437\/revisions\/5152"}],"wp:attachment":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/media?parent=3437"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/categories?post=3437"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/tags?post=3437"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}