{"id":2062,"date":"2018-05-29T13:15:04","date_gmt":"2018-05-29T11:15:04","guid":{"rendered":"https:\/\/www.primanedacademy.com\/?p=2062"},"modified":"2018-05-29T13:29:54","modified_gmt":"2018-05-29T11:29:54","slug":"project-calendars-over-global-calendars","status":"publish","type":"post","link":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/","title":{"rendered":"Project Calendars over Global Calendars"},"content":{"rendered":"<p>Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects. In order to achieve this Primavera P6 uses the concept of \u201cGlobal\u201d data objects and \u201cProject\u201d (or embedded) data objects.<\/p>\n<p>In this blog I will show you why using a project calendar over a global calendar for your project activities schedule is beneficial to maintain control over your project(s).<\/p>\n<p><!--more--><\/p>\n<h3>Calendars<\/h3>\n<p>A calendar is used to define working and non-working periods. Weekends, holidays and other project specific non-working days can be defined. It is even possible to go into further detail and define working hours per day. Users can create for each work pattern a fitting calendar.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-2063 size-medium\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_01-300x288.png\" alt=\"\" width=\"300\" height=\"288\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_01-300x288.png 300w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_01.png 561w\" sizes=\"auto, (max-width: 300px) 100vw, 300px\" \/> <img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-2064 size-medium\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_02-300x252.png\" alt=\"\" width=\"300\" height=\"252\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_02-300x252.png 300w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_02.png 727w\" sizes=\"auto, (max-width: 300px) 100vw, 300px\" \/><\/p>\n<p>Calendars can be assigned to each resource and activity to determine time constraints in a uniform way. Primavera P6 uses your calendar assignments for scheduling, levelling resources and tracking activities.<\/p>\n<p>Three types of calendars are supported:<\/p>\n<ul>\n<li><strong>Global Calendar: <\/strong>can be assigned to a project, activities and resources<\/li>\n<li><strong>Project Calendar: <\/strong>can be assigned to a specific project and or its activities<\/li>\n<li><strong>Resource Calendar: <\/strong>only for resources (will not be discussed further in this blog)<\/li>\n<\/ul>\n<h3>Global Calendars<\/h3>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter wp-image-2065 size-full\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_03.png\" alt=\"\" width=\"600\" height=\"340\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_03.png 600w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_03-300x170.png 300w\" sizes=\"auto, (max-width: 600px) 100vw, 600px\" \/><\/p>\n<h3>Advantages<\/h3>\n<ul>\n<li>Global calendars exist outside of all projects.<br \/>\nWhen an associated project is deleted the Global Calendar will not be deleted.<\/li>\n<li>Global calendars can be left out during an import process. This is often forgotten though.<\/li>\n<li>When a user changes a Global Calendar these changes are applied to all projects using that Global Calendar. This can be useful when using a calendar on activities which are influenced by weather. For example, we could define a global calendar for concrete works on multiple projects.<\/li>\n<\/ul>\n<h3>Disadvantages<\/h3>\n<ul>\n<li>The most important disadvantage why not to use global calendars is what happens when importing a project (XER file):\n<ul>\n<li>project specific data is added to the database (embedded data)<\/li>\n<li>at the same time, all linked global data in the file, is also inserted into existing global data in the receiving database.<\/li>\n<li>after importing numerous projects this will lead to a polluted Global Calendar register. To remain organized a user must purge the register systematically and use a standard naming convention for his calendars.<\/li>\n<\/ul>\n<\/li>\n<li>When a user changes a Global Calendar for a specific project, these changes are applied to all project using that Global Calendar. This often leads to unintentional changes for other projects using this calendar.<\/li>\n<li>Back-ups (copies) of your projects functioning can change when linked to a global calendar which is altered, so in fact no longer functions as back-ups. Nuance: dates will only change when you recalculate (F9) a project.<\/li>\n<li>After importing several projects with Global Calendars the library will get various names for the same calendars, which will look and feel messy for the user. For example, a basic 7-day calendar can be labeled in various ways:\n<ul>\n<li>7 x 8<\/li>\n<li>7x 8<\/li>\n<li>7 day calendar<\/li>\n<li>Seven day calendar<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n<ul>\n<li>When exporting a project that uses Global Calendars, they also wind up in the Global Calendars list of the recipient who imports the project. After several imports this can lead to a cluttered library.<\/li>\n<li>When analyzing the quality of a planning in Primavera often one of the first steps is to make an inventory of the used Calendars. Some applied Global Calendars may be overlooked when they are hidden in a cluttered library of Global Calendars.<\/li>\n<li>Importing a project with a Global Calendar that has an identical name to an existing calendar in your database will give an unexpected result. Primavera P6 will not overwrite the existing calendar when importing which can give different outcomes of the same schedule for both users.<\/li>\n<\/ul>\n<h3>Project Calendars<\/h3>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"size-full wp-image-2066 aligncenter\" src=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png\" alt=\"\" width=\"600\" height=\"392\" srcset=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png 600w, https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04-300x196.png 300w\" sizes=\"auto, (max-width: 600px) 100vw, 600px\" \/><\/p>\n<p>If the project calendar is linked to the global calendar, then any change made in the global calendar will be reflected in the project calendar but not vice versa.<\/p>\n<h3>Conclusion<\/h3>\n<p>Global calendars are a powerful asset in a multiple project environment if implementation is done flawlessly by all users. (Un)fortunately we are only human and we often make mistakes.<br \/>\nThe impact of all these errors in time, when managing global data in an enterprise, will ultimately result in a polluted database and unintentional mistakes on a project level.<\/p>\n<p>That is why in many multi-national enterprises the importing of Primavera P6 projects into their central P6 database is under strict control by an administrator.<\/p>\n<p>Working with project calendars takes away these risks.<\/p>\n<p>A global calendar is a powerful tool for businesses who manage projects where weather downtime plays a major part. Such a calendar is often used based upon experience from previous projects and weather statistics. Examples are off-shore projects, outdoor activities in construction, etc. A small error in these calendars can mean losses in hundred thousands.<\/p>\n<p>This blog is originally placed on\u00a0<a href=\"https:\/\/primaned.be\/en\/going-slower-to-finish-faster\/\">Primaned.be<\/a>\u00a0op 18 May.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects. In order to achieve this Primavera P6 uses the concept of \u201cGlobal\u201d data objects and \u201cProject\u201d (or embedded) [&hellip;]<\/p>\n","protected":false},"author":14,"featured_media":2066,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"_monsterinsights_skip_tracking":false,"_monsterinsights_sitenote_active":false,"_monsterinsights_sitenote_note":"","_monsterinsights_sitenote_category":0,"footnotes":""},"categories":[87],"tags":[136],"class_list":["post-2062","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog-en","tag-oracle-primavera"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.4 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Project Calendars over Global Calendars - Primaned Academy<\/title>\n<meta name=\"description\" content=\"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/\" \/>\n<meta property=\"og:locale\" content=\"en_GB\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Project Calendars over Global Calendars - Primaned Academy\" \/>\n<meta property=\"og:description\" content=\"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/\" \/>\n<meta property=\"og:site_name\" content=\"Primaned Academy\" \/>\n<meta property=\"article:published_time\" content=\"2018-05-29T11:15:04+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2018-05-29T11:29:54+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png\" \/>\n\t<meta property=\"og:image:width\" content=\"600\" \/>\n\t<meta property=\"og:image:height\" content=\"392\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Matthijs Warnez\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Matthijs Warnez\" \/>\n\t<meta name=\"twitter:label2\" content=\"Estimated reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/\"},\"author\":{\"name\":\"Matthijs Warnez\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/a58733c17a2d4d904f9a662d41e23f14\"},\"headline\":\"Project Calendars over Global Calendars\",\"datePublished\":\"2018-05-29T11:15:04+00:00\",\"dateModified\":\"2018-05-29T11:29:54+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/\"},\"wordCount\":809,\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/20180518_MWA_afbeelding_04.png\",\"keywords\":[\"Oracle Primavera\"],\"articleSection\":[\"Blog - EN\"],\"inLanguage\":\"en-GB\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/\",\"name\":\"Project Calendars over Global Calendars - Primaned Academy\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/20180518_MWA_afbeelding_04.png\",\"datePublished\":\"2018-05-29T11:15:04+00:00\",\"dateModified\":\"2018-05-29T11:29:54+00:00\",\"author\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/a58733c17a2d4d904f9a662d41e23f14\"},\"description\":\"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#breadcrumb\"},\"inLanguage\":\"en-GB\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/20180518_MWA_afbeelding_04.png\",\"contentUrl\":\"https:\\\/\\\/www.primanedacademy.com\\\/wp-content\\\/uploads\\\/20180518_MWA_afbeelding_04.png\",\"width\":600,\"height\":392},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/project-calendars-over-global-calendars\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Project Calendars over Global Calendars\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#website\",\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/\",\"name\":\"Primaned Academy\",\"description\":\"Opleidingen in Projectbeheersing \\\/ Project Controls\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.primanedacademy.com\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-GB\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.primanedacademy.com\\\/#\\\/schema\\\/person\\\/a58733c17a2d4d904f9a662d41e23f14\",\"name\":\"Matthijs Warnez\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-GB\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g\",\"caption\":\"Matthijs Warnez\"},\"url\":\"https:\\\/\\\/www.primanedacademy.com\\\/en\\\/author\\\/matthijs\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Project Calendars over Global Calendars - Primaned Academy","description":"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/","og_locale":"en_GB","og_type":"article","og_title":"Project Calendars over Global Calendars - Primaned Academy","og_description":"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.","og_url":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/","og_site_name":"Primaned Academy","article_published_time":"2018-05-29T11:15:04+00:00","article_modified_time":"2018-05-29T11:29:54+00:00","og_image":[{"width":600,"height":392,"url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png","type":"image\/png"}],"author":"Matthijs Warnez","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Matthijs Warnez","Estimated reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#article","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/"},"author":{"name":"Matthijs Warnez","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/a58733c17a2d4d904f9a662d41e23f14"},"headline":"Project Calendars over Global Calendars","datePublished":"2018-05-29T11:15:04+00:00","dateModified":"2018-05-29T11:29:54+00:00","mainEntityOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/"},"wordCount":809,"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png","keywords":["Oracle Primavera"],"articleSection":["Blog - EN"],"inLanguage":"en-GB"},{"@type":"WebPage","@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/","url":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/","name":"Project Calendars over Global Calendars - Primaned Academy","isPartOf":{"@id":"https:\/\/www.primanedacademy.com\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#primaryimage"},"image":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#primaryimage"},"thumbnailUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png","datePublished":"2018-05-29T11:15:04+00:00","dateModified":"2018-05-29T11:29:54+00:00","author":{"@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/a58733c17a2d4d904f9a662d41e23f14"},"description":"Primavera P6 is designed as an Enterprise Project Portfolio Management (EPPM) tool.\u00a0Even though often used as a standalone tool, Primavera P6 is a database initially designed for the enterprise\u2019s needs where data can be shared between projects.","breadcrumb":{"@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#breadcrumb"},"inLanguage":"en-GB","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/"]}]},{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#primaryimage","url":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png","contentUrl":"https:\/\/www.primanedacademy.com\/wp-content\/uploads\/20180518_MWA_afbeelding_04.png","width":600,"height":392},{"@type":"BreadcrumbList","@id":"https:\/\/www.primanedacademy.com\/en\/project-calendars-over-global-calendars\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.primanedacademy.com\/en\/"},{"@type":"ListItem","position":2,"name":"Project Calendars over Global Calendars"}]},{"@type":"WebSite","@id":"https:\/\/www.primanedacademy.com\/#website","url":"https:\/\/www.primanedacademy.com\/","name":"Primaned Academy","description":"Opleidingen in Projectbeheersing \/ Project Controls","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.primanedacademy.com\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-GB"},{"@type":"Person","@id":"https:\/\/www.primanedacademy.com\/#\/schema\/person\/a58733c17a2d4d904f9a662d41e23f14","name":"Matthijs Warnez","image":{"@type":"ImageObject","inLanguage":"en-GB","@id":"https:\/\/secure.gravatar.com\/avatar\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/6a040544b01d49d7c3ad110328995cee1e6b3a707cdfd845f4a59993903fdeb2?s=96&d=mm&r=g","caption":"Matthijs Warnez"},"url":"https:\/\/www.primanedacademy.com\/en\/author\/matthijs\/"}]}},"_links":{"self":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/2062","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/users\/14"}],"replies":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/comments?post=2062"}],"version-history":[{"count":3,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/2062\/revisions"}],"predecessor-version":[{"id":2169,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/posts\/2062\/revisions\/2169"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/media\/2066"}],"wp:attachment":[{"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/media?parent=2062"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/categories?post=2062"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.primanedacademy.com\/en\/wp-json\/wp\/v2\/tags?post=2062"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}